Why Invest in a High-Quality Make Ready?

<aside> 💡

Check out our video about our Make Ready program here!

</aside>

Our experience and data have consistently proven the value of performing high-quality make readies before listing a property. Owners who invest in a proper make ready see measurable returns through faster leasing, higher rents, and better tenants.

The SPM Make Ready Advantage

See the Appendix for a detailed financial comparison of SPM Make Ready vs. Owner Make Ready, including a 12-month NOI analysis.


Make Ready Timeline (14 Days to Market)

If owner approval is received within 2 business days of the estimate, here's how our make ready process works:

Milestone Timeline
Inspection & Estimate Sent Days 1–3 (within 3 days of move-out or onboarding)
Owner Estimate Approval Day 4 (we ask for approval within 2 business days)
Work Scheduled & Begins Day 6 (within 3 business days of written approval + 50% deposit)
Work Completed Day 9 (80%+ of projects completed within 3 business days of start)
Cleaners & Photos Days 10–12 (photos typically take 1 full day to edit and process)
Listed on Market Day 14 (takes ~24 hours to appear on 30+ marketing websites)

Note: Prompt approval is critical. Every day of delay in the approval stage adds directly to vacancy time.


Make Ready Costs

How We Calculate Costs Make ready estimates are broken down into three categories: Labor, Materials, and Overhead.